The Union Cabinet announced on 4 November 2026 the approval of a Viability Gap Funding (VGF) Scheme to develop 92 GWh of grid-scale energy storage systems. With a total financial support of Rs 14,500 crore, the scheme targets 60 GWh of Hydro Pumped Storage, 30 GWh of Battery Energy Storage Systems (BESS), and 2 GWh of alternative technologies. The program runs from FY 2026-27 to FY 2030-31 and aims to help India reach a total capacity of 411 GWh by 2031-32. Public and private sector electricity distribution companies and other entities can apply through a competitive bidding process.
Key points
- Total funding: Rs 14,500 crore for the period FY 2026-27 to FY 2030-31
- Target: 92 GWh total capacity (60 GWh Hydro PSP, 30 GWh BESS, 2 GWh alternative)
- BESS projects must have at least 40% domestic content
- Eligible: Public and private sector electricity distribution companies and entities
- Selection: Capacity will be allocated via tariff-based competitive bidding
When it applies
- VGF Scheme financial support period
- VGF Scheme financial support period
- target to meet Grid Scale ESS capacity of 411 GWh
Who it affects
- BESS projects
- Public and private sector electricity distribution companies and other entities