The Department of Atomic Energy announced on 20 November 2026 that the Atomic Energy Regulatory Board (AERB) granted permission for the First Approach to Criticality (FAC) of Rajasthan Atomic Power Project Unit-8 (RAPP-8) on 19 November 2026. This permission follows safety reviews of the reactor's design, construction, and operational readiness. The FAC is a key commissioning step that allows the 700 MWe Pressurised Heavy Water Reactor to move toward commercial electricity generation. The unit is located at the Rawatbhata Nuclear Power Plant site in Rajasthan.
Key points
- Permission granted on 19 Nov 2026 for First Approach to Criticality (FAC) of RAPP-8
- RAPP-8 is an indigenously designed 700 MWe Pressurised Heavy Water Reactor (PHWR)
- Located at Rawatbhata Nuclear Power Plant site, Chittorgarh district, Rajasthan
- Approval follows comprehensive safety reviews of design, construction, and commissioning tests
When it applies
- granting of permission for First Approach to Criticality (FAC)
Who it affects
- nuclear power plant unit