The Ministry of Statistics and Programme Implementation (MoSPI) announced on 25 November 2026 that it is monitoring 1,862 Central Sector infrastructure projects with a total cost of ₹38.11 lakh crore using the PAIMANA platform. As of October 2026, ₹17.87 lakh crore (approximately 46.88%) has been spent on these projects, which are spread across 17 Central Ministries and Departments. The Transport and Logistics and Energy sectors make up 83.41% of the total projects. The report covers projects with a cost of ₹150 crore and above.
Key points
- Total projects monitored: 1,862 with a total cost of ₹38.11 lakh crore.
- Cumulative expenditure: ₹17.87 lakh crore (46.88% of total cost).
- Sector focus: Transport & Logistics (1,324 projects) and Energy (229 projects).
- Project scale: 790 Mega projects (₹1,000 crore+) and 1,072 Major projects (below ₹1,000 crore).
- Next report: Flash Report for November 2026 will be released on 28 December 2026.
When it applies
- release of Flash Report for the month of November 2026
- commissioning of Transmission Scheme for Integration of Renewable Energy Zone [Phase II] in Koppal II [Phase A&B] and Gadag II [Phase A] in Karnataka
- commissioning of Six lane Elevated Corridor on NH-66
- commissioning of Rebuilding of Coke Oven Battery No.7 & 8 at Bhilai Steel Plant
Who it affects
- Central Sector infrastructure projects