The Ministry of Railways announced on 27 November 2026 that Indian Railways has completed the main tunnel breakthrough of Tunnel-14, a 6.59 km tunnel on the Rishikesh-Karnaprayag Rail Project, in Rudraprayag district of Uttarakhand. The breakthrough joins the two excavated sections of the tunnel: 4.7 km dug from Portal-1 at Sumerpur and 1.79 km from Portal-2 at Marora. The ministry describes the project as aimed at improving rail connectivity in Uttarakhand, including for pilgrims, tourists and hill regions. The release does not say when the rail line itself will open.
Key points
- Tunnel-14 breakthrough completed on 27 Nov 2026 in Rudraprayag district, Uttarakhand.
- Tunnel is 6.59 km long; 4.7 km excavated from Portal-1 (Sumerpur), 1.79 km from Portal-2 (Marora).
- A 110-metre stretch of the triple-track tunnel was dug through loose soil under inhabited areas.
- Main tunnel drive from Portal-2 launched in March 2024 after ground settlement issues were resolved.
When it applies
- Tunnel-14 main tunnel breakthrough