The Ministry of Railways said on 28 November 2026 that Indian Railways completed excavation of Tunnel No. 10, a 5.3-km tunnel, on 27 November 2026, finishing excavation of all 14 tunnels of the Sivok-Rangpo new line project. The 45-km broad gauge line will pass through Darjeeling and Kalimpong districts in West Bengal and Pakyong district in Sikkim, with 14 tunnels covering about 86% of the route and 23 bridges. It will serve Sivok, Riyang, Melli and Rangpo stations plus an underground halt at Teesta Bazaar, connecting Sikkim to the national railway network. Work remaining includes tunnel lining, track laying and railway safety systems. The release does not say when the line will open.
Key points
- Tunnel No. 10, 5.3 km long, is the longest of 14 tunnels; excavation finished 27 Nov 2026
- 45-km broad gauge Sivok-Rangpo line; tunnels cover ~86% of the route
- Project includes 23 bridges and stations at Sivok, Riyang, Melli and Rangpo, plus a Teesta Bazaar halt
- Line to give Sikkim direct railway connectivity via a link at Sivok
- Remaining work: tunnel lining, track laying and safety system installation
When it applies
- Breakthrough and completion of excavation in Tunnel No. 10